20’’ inch, 120km Tendrara Gas Export Pipeline ("TGEP"):
- Tie-in to existing GME pipeline (Station M04): FEED completed by Metragaz (EMPL operator)
- Pipeline EIA permit approved
- 70 mmscf/d raw gas CPF processing capacity: FEED completed by Enagás Consortium
- CPF EIA permit approved
- Gas Sales Agreement ("GSA") with ONEE (Office National de l'Electricite et de l'Eau potable) signed November 2021 for domestic power plants for gas-to-power generation (transit via GME line), minimum volume of 0.3 bcm/year
- Six horizontal wells planned for First Gas (Phase 2)